Dining Hall For Kaiwara Temple – Kaiwara

Area : B + G – 60,000 ft2 area

Scope : Design and Built including all finishes (Turn Key)

Elements : CIS footings, 200mm thick precast concrete retaining walls for basement, 500 mm x 500mm double height columns, 160mm thick load bearing precast concrete walls, RCC Beams, Pre stressed Hollow Core slabs of 300mm/265mm/200mm thick, precast stair flight and landing slabs.

Program of Completion : Sub and superstructure using precast – 4 months

Finishes : Granite Flooring, UPVC Window/ Doors, Teak wood Doors, Schindler Lift, Asian Paint, False ceiling acoustic/Grid, MEP, Glazing, Water proofing

Finishes Completion : 05 months

Overall Completion : 09 Months